River Great Ouse: Flood Control

Commons · Question 28893 · Tabled 10 Sep 2026 · Department for Environment, Food and Rural Affairs · Official record

Answered 17 Sep 2026

Question

Asked by Ben Obese-Jecty

To ask the Secretary of State for Environment, Food and Rural Affairs, what steps further to those previously anticipated are needed by the Environment Agency to justify and gain approval to deliver the replacement of St Ives sluice.

Answer

Answered by Emma Hardy, 17 Sep 2026

St Ives Sluice is progressing through the Environment Agency full business case approval process. The fixed weir option currently provides the best whole life cost solution.