Asked by Baroness Deech

To ask His Majesty's Government what is the (1) original, and (2) current, estimated cost of the update to Oxford station, including the new western entrance and platform five.

Answer

Answered by Lord Hendy of Richmond Hill, 16 Sep 2026

The original cost for the Oxford station enhancement project was £161 million. The estimated cost is £237.4 million. This does not include the full cost of the final delivery phase of the project, including the new western entrance and platform five which...