Written questions

Electricity Generation: Infrastructure

2026-07-21 · Department for Energy Security and Net Zero · HL2613 · Official question

Question

To ask His Majesty's Government how many transmission connection projects in the Transmission Entry Capacity register have been completed to date, out of the total number currently in the queue.

Answer

According to National Energy System Operator (NESO), as of 24 July, the Transmission Entry Capacity (TEC) Register included 373 generation projects that have been built. 1,026 generation projects have received revised ‘Gate 2’ connection offers (confirmed...