Electricity Generation: Infrastructure
2026-07-21 · Department for Energy Security and Net Zero · HL2614 · Official question
Question
To ask His Majesty's Government what proportion of Transmission Entry Capacity projects due for delivery by 2030 do not yet have a corresponding entry in the Transmission Works Report.
Answer
The Transmission Works Report (TWR) is being updated in light of revised connection offers issued as part of the connections reform process. All projects that accept a ‘Gate 2’ connection offer (confirmed connection location and date) will have a correspo...