Project Gigabit: Mid Bedfordshire
Commons · Question 15089 · Tabled 1 Jul 2026 · Department for Science, Innovation and Technology · Official record
Answered 9 Jul 2026
Question
Asked by Blake Stephenson
To ask the Secretary of State for Science, Innovation and Technology, if she will ensure that the 5,443 properties descoped from Project Gigabit in Mid Bedfordshire constituency in May 2026 are added to a future programme.
Answer
Answered by Kanishka Narayan, 9 Jul 2026
As a result of the recent changes agreed by Building Digital UK (BDUK) and CityFibre, the earlier stages of the Bedfordshire, Northamptonshire and Milton Keynes contract will proceed as planned, and premises in the later stages will be removed from the co...