High Speed 2 Line: Iron and Steel
2026-06-22 · Department for Transport · HL1225 · Official question
Question
To ask His Majesty's Government what percentage of the total steel requirement for HS2 has been procured.
Answer
94% of structural steel and 90% of the steel rebar required for the HS2’s Main Works Civils has been procured. Assessments from the Main Works Contractors working on the Civils structures indicate that around 70% of Rebar and over 80% of Structural Steel ...