Commons · Question 12229 · Tabled 23 Jun 2026 · Department for Transport · Official record

Answered 1 Jul 2026

Question

Asked by Jerome Mayhew

To ask the Secretary of State for Transport, how many rail infrastructure projects in England with a capital value below £50 million are behind schedule.

Answer

Answered by Simon Lightwood, 1 Jul 2026

Network Rail is delivering hundreds of projects across the country to maintain and upgrade the rail network. Of the projects currently delivering on site with an anticipated cost of less than £50 million, 144 are currently forecasting to complete after th...