Large Goods Vehicles: Electric Vehicles
Commons · Question 8840 · Tabled 10 Jun 2026 · Department for Transport · Official record
Answered 18 Jun 2026
Question
Asked by Joe Robertson
To ask the Secretary of State for Transport, what estimate her Department has made of the costs associated with (a) on-site battery storage and (b) depot infrastructure upgrades required to support the charging of zero-emission heavy goods vehicles.
Answer
Answered by Keir Mather, 18 Jun 2026
The Department recognises that the costs associated with enabling infrastructure for zero emission heavy goods vehicles (HGVs), including on‑site battery storage and depot upgrades, are an important consideration for operators. Single estimates of these c...