Written questions

High Speed 2 Line

Commons · Question 8115 · Tabled 9 Jun 2026 · Department for Transport · Official record

Answered 17 Jun 2026

Question

Asked by Jerome Mayhew

To ask the Secretary of State for Transport, pursuant to the Answer of 5 June 2026 to Question 3549 on High Speed 2 Line, when she expects the updating of the HS2 programme business case and the resetting of the benefits baseline to be completed; and whet

Answer

Answered by Simon Lightwood, 17 Jun 2026

DfT and HS2 Ltd are currently in the process of updating the programme business case and resetting the benefits baseline in line with the ongoing programme reset, which should be complete by Spring 2027. The programme benefits and how HS2 will realise the...