Written questions

Thameslink Line: Rolling Stock

Commons · Question 7520 · Tabled 8 Jun 2026 · Department for Transport · Official record

Answered 15 Jun 2026

Question

Asked by Jerome Mayhew

To ask the Secretary of State for Transport, what the completion schedule is for the deep cleaning, minor repairs, and toilet resurfacing across all 115 Class 700 units on Thameslink: and what anti-graffiti measures are being introduced during this refres

Answer

Answered by Keir Mather, 15 Jun 2026

On 31 May 2026, the Thameslink Service transferred into public ownership to deliver more reliable, passenger-centred services across the network. As part of a programme of planned improvements, the train operator is wrapping Thameslink train toilets with ...