High Speed 2 Line: Euston Station

Commons · Question 6760 · Tabled 4 Jun 2026 · Department for Transport · Official record

Answered 15 Jun 2026

Question

Asked by Wendy Morton

To ask the Secretary of State for Transport, what estimate she has made of the cost of delivering HS2 Euston station; how much of that cost is included within the £87.7 billion to £102.7 billion cost range announced on 19 May 2026; and what proportion of

Answer

Answered by Simon Lightwood, 15 Jun 2026

Drawing on lessons learned from previous experience, the Department is taking the time to complete the necessary work to establish a robust baseline before seeking to set budgets for Euston. Our private finance and funding package for Euston includes op...