Accident and Emergency Departments
Commons · Question 3704 · Tabled 20 May 2026 · Department of Health and Social Care · Official record
Answered 4 Jun 2026
Question
Asked by James McMurdock
To ask the Secretary of State for Health and Social Care, with reference to the Answer of 14 April 2026 to Question 120732, what the planned completion timelines are for the 40 funded schemes.
Answer
Answered by Karin Smyth, 4 Jun 2026
Of the 14 Urgent Treatment Centre (UTC) projects, comprising of 10 new UTCs and four UTC expansions, one scheme has already been delivered, 12 are scheduled for delivery between May and October 2026, and the final multi-year scheme is expected to be compl...