Written questions

Railway Stations: Barking

Commons · Question 3403 · Tabled 20 May 2026 · Department for Transport · Official record

Answered 8 Jun 2026

Question

Asked by Greg Smith

To ask the Secretary of State for Transport, what progress c2c has made on upgrading Barking station since 17 December 2025; and whether the upgraded ticket office, new lift and extended gateline remain on schedule for completion in 2026.

Answer

Answered by Keir Mather, 8 Jun 2026

c2c continue to make positive progress on the Barking station upgrade. Since 17 December 2025, both gatelines have been installed and are operational, the upgraded ticket office is 95% complete and the lift works are complete with lifts returning to servi...