Transport: Infrastructure
Commons · Question 1568 · Tabled 14 May 2026 · Department for Transport · Official record
Answered 27 May 2026
Question
Asked by Andrew Snowden
To ask the Secretary of State for Transport, what transport infrastructure projects in the 2024 Labour Party manifesto have been (a) completed, (b) commenced, (c) delayed or (d) cancelled.
Answer
Answered by Simon Lightwood, 27 May 2026
The 2024 Labour Party election manifesto made the following two pledges for transport infrastructure projects. To fix an additional 1 million potholes across England each year, funded by reallocating money from the previously cancelled A27 bypass. We are ...