Asked by Jerome Mayhew
To ask the Secretary of State for Transport, pursuant to the Answer of 26 March 2026 to Question 122316, whether Network Rail plans to publish the further timetabling analysis and modelling referred to in that Answer; and if she will place a copy in the L
Answer
Answered by Keir Mather, 20 Apr 2026
The Department has worked extensively with Network Rail and stakeholders on development and design of a scheme to deliver a third line between York North Throat and Skelton Junction. The scheme remains under review to ensure it can be delivered in the mos...