M6: Repairs and Maintenance
Commons · Question 126106 · Tabled 10 Apr 2026 · Department for Transport · Official record
Answered 20 Apr 2026
Question
Asked by Joe Robertson
To ask the Secretary of State for Transport, what the total duration in hours was of (a) partial and (b) full closures as a result of the M6 Lune Gorge project.
Answer
Answered by Simon Lightwood, 20 Apr 2026
Between 1 September 2025 and 14 April 2026, all recorded closures associated with preparatory works were partial closures only, affecting a single northbound or southbound carriageway, or lane closures. There were 18 overnight carriageway closures, each o...