Question

Asked by Tom Gordon

To ask the Secretary of State for Transport, what assessment has been made of the impact of the train capacity through York train station as a result of the TransPennine Route Upgrade on the level of timeliness at Skelton Junction.

Answer

Answered by Keir Mather, 26 Mar 2026

Train capacity through York Station is the subject of the York Area Capacity and Performance Project which was paused at the Spending Review. The scope of the TransPennine Route Upgrade Programme excludes York Station itself. Network Rail are undertaking ...