Question
Asked by Ben Obese-Jecty
To ask the Secretary of State for Defence, pursuant to the answer of 9 September 2025 to question 73557 on Navy: Dockyards, what progress he has made in delivering the NSIGN Projects to enable the Ministry of Defence to contract for Submarine and enabling
Answer
Answered by Luke Pollard, 16 Apr 2026
Good progress has been made on both programmes. Contract placement is on track to extend the Future Maritime Support Programme (FMSP) to cover the period from April 2026 up to October 2028. The extension will ensure a smooth transition to the Naval Suppor...