Armoured Fighting Vehicles: Procurement
Commons · Question 116387 · Tabled 26 Feb 2026 · Ministry of Defence · Official record
Answered 6 Mar 2026
Question
Asked by Ben Obese-Jecty
To ask the Secretary of State for Defence, what is the delivery timeline for the (a) 61 M270 MLRS launchers and (b) eight Repair and Recovery vehicles.
Answer
Answered by Luke Pollard, 6 Mar 2026
The Multiple Launch Rocket Systems launchers and Repair and Recovery Vehicles (RRVs) are on contract to be upgraded to the A2 standard. Two launchers have now been delivered to the UK and a further 13 launchers and two RRVs are currently on the production...