Palace of Westminster: Repairs and Maintenance
Commons · Question 115410 · Tabled 24 Feb 2026 · Restoration and Renewal Client Board · Official record
Answered 3 Mar 2026
Question
Asked by Wendy Morton
To ask the hon. Member for Blaenau Gwent and Rhymney, representing the Restoration and Renewal Client Board, with reference to the cost ranges set out in Table 1 of the costed proposals report, what assessment the Client Board has made of the historical a
Answer
Answered by Nick Smith, 3 Mar 2026
The recent report from the Restoration and Renewal (R&R) Client Board, Delivering restoration and renewal of the Palace of Westminster: the costed proposals (HC Paper 1576), provides costs and schedules as ranges at different confidence levels (P50 an...