Question

Asked by Baroness Boycott

To ask His Majesty's Government what assessment they have made of reports that Ofgem has said that the volume of grid connection applications from data centres “exceeds even the most ambitious demand forecasts” and will put at risk meeting carbon budgets.

Answer

Answered by Lord Whitehead, 9 Mar 2026

As Ofgem states in its recent publication, Government is working closely with the regulator, NESO, and network companies, to develop and deliver a coordinated package of reforms to the grid connection process for demand projects. This includes measures de...