Commons · Question 109850 · Tabled 30 Jan 2026 · Department for Science, Innovation and Technology · Official record

Answered 4 Feb 2026

Question

Asked by Helen Morgan

To ask the Secretary of State for Science, Innovation and Technology, what date the last premises in North Shropshire was connected to full fibre under Project Gigabit; and the date on which the next connection is planned.

Answer

Answered by Kanishka Narayan, 4 Feb 2026

In North Shropshire constituency, the last premises connected by Freedom Fibre’s Project Gigabit contract covering North Shropshire was on the 30 June 2025, whilst the last premises connected under the Gigabit Broadband Voucher Scheme was on the 28 July 2...