Question

Asked by Andrew Rosindell

To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the answer of 21 January 2026 to question UIN 104660, what the average time was between receipt of a regulation 21 change control application by the BSR and notificat

Answer

Answered by Samantha Dixon, 2 Feb 2026

Notifiable or Major Change notifications are added to existing applications which are already in build and have been determined with approval granted. As such, Major or Notifiable works are not treated as new applications and the time taken is not reporte...