River Great Ouse: Flood Control

Commons · Question 106660 · Tabled 19 Jan 2026 · Department for Environment, Food and Rural Affairs · Official record

Answered 27 Jan 2026

Question

Asked by Ben Obese-Jecty

To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the answer of 19 January 2026, to question 104939 on River Great Ouse: Flood Control, by when will phase 1 of the gate refurbishment project be completed.

Answer

Answered by Emma Hardy, 27 Jan 2026

Phase 1 of the gate refurbishment project is expected to be completed by 31 March 2026.