Department for Education: Research
Commons · Question 106036 · Tabled 14 Jan 2026 · Department for Education · Official record
Answered 26 Feb 2026
Question
Asked by Rupert Lowe
To ask the Secretary of State for Education, what the cost to the public purse was of feasibility studies conducted by their Department for projects that did not proceed in the last five years.
Answer
Answered by Olivia Bailey, 26 Feb 2026
The cost of feasibility studies conducted by the department on school building capital projects that did not proceed in the last 5 years is £8,689,888.These costs are made up of capital funding, property costs, professional and technical services, staff a...