Ajax Vehicles: Procurement
Commons · Question 105652 · Tabled 14 Jan 2026 · Ministry of Defence · Official record
Answered 20 Apr 2026
Question
Asked by Gregory Campbell
To ask the Secretary of State for Defence, how much expenditure has been incurred on the Ajax programme since the decision was taken to pause it in 2025.
Answer
Answered by Luke Pollard, 20 Apr 2026
The Ministry of Defence has paid £46 million, in line with contractual obligations, for the Ajax programme between 23 November 2025 and 14 January 2026. It is not possible to release a breakdown of these payments as this information is considered commerci...