Question

Asked by Ben Obese-Jecty

To ask the Secretary of State for Defence, pursuant to the answer of 5 January to Question to 100522, on General Dynamics, what additional steps were taken by him from (a) 23 July 2025 and separately from (b) 15 September 2025, in order to assess that Aja

Answer

Answered by Luke Pollard, 13 Jan 2026