Renewable Energy: National Grid
Lords · Question HL11120 · Tabled 20 Oct 2025 · Department for Energy Security and Net Zero · Official record
Answered 3 Nov 2025
Question
Asked by Lord Bradshaw
To ask His Majesty's Government by what date they expect the National Grid to have sufficiently updated capacity to use or store the power available from renewable sources.
Answer
Answered by Lord Wilson of Sedgefield, 3 Nov 2025
We are working closely with Ofgem and National Energy System Operator (NESO) to deliver an electricity network ready for clean power by 2030 and beyond, accelerating infrastructure delivery by reforming planning, regulation and supply chains. The same is ...