Written questions

Railways: East of England

Commons · Question 82839 · Tabled 16 Oct 2025 · Department for Transport · Official record

Answered 27 Oct 2025

Question

Asked by Charlotte Cane

To ask the Secretary of State for Transport, what progress she has made on the Ely Junction Upgrade Scheme.

Answer

Answered by Keir Mather, 27 Oct 2025

The Ely Area Capacity Enhancement (EACE) programme was paused by the previous government in 2022. The Secretary of State updated Parliament on the 7th of July on which rail and road infrastructure projects will proceed following the 2025 Spending Review.A...