Written questions

Solar Power

Commons · Question 73291 · Tabled 29 Aug 2025 · Department for Energy Security and Net Zero · Official record

Answered 8 Sep 2025

Question

Asked by Martin Wrigley

To ask the Secretary of State for Energy Security and Net Zero, whether the National Grid is under a (a) statutory and (b) regulatory obligation to process solar panel installation applications within a specified timeframe.

Answer

Answered by Michael Shanks, 8 Sep 2025

For solar installations of 3.68kW per phase, or below, no application is required. The Distribution Network Operator (DNO) must only be notified within 30 days of the installation. For larger projects, DNOs are required to provide a connection offer withi...