Asked by Martin Wrigley
To ask the Secretary of State for Energy Security and Net Zero, whether the National Grid is under a (a) statutory and (b) regulatory obligation to process solar panel installation applications within a specified timeframe.
Answer
Answered by Michael Shanks, 8 Sep 2025
For solar installations of 3.68kW per phase, or below, no application is required. The Distribution Network Operator (DNO) must only be notified within 30 days of the installation. For larger projects, DNOs are required to provide a connection offer withi...