South West Main Line: Devon
Commons · Question 69599 · Tabled 21 Jul 2025 · Department for Transport · Official record
Answered 3 Sep 2025
Question
Asked by Martin Wrigley
To ask the Secretary of State for Transport, pursuant to the Answer of 17 July 2025 to Question 66340 on the South West Rail Resilience Programme, whether her Department has received the assessments completed by Network Rail in 2024 on the outline design
Answer
Answered by Simon Lightwood, 3 Sep 2025
Following receipt of the Outline Business Case for Phase 5 of the Resilience Programme from Network Rail in 2024, the Department is funding further cliff monitoring and drainage works on this section of route. The project will be kept under review at futu...