Written questions

South West Main Line: Devon

Commons · Question 66347 · Tabled 9 Jul 2025 · Department for Transport · Official record

Answered 17 Jul 2025

Question

Asked by Martin Wrigley

To ask the Secretary of State for Transport, whether her Department has set a deadline for Network Rail to produce a revised proposal for Phase 5 of the South West Rail Resilience Programme.

Answer

Answered by Simon Lightwood, 17 Jul 2025

We are continuing to fund drainage and ground investigations that will provide Network Rail with detailed data on the stability of the cliffs above that section of route and will inform their consideration of a proposal for a long-term solution in due cou...