Question

Asked by Martin Wrigley

To ask the Secretary of State for Transport, what steps her Department plans to take to improve resilience along the stretch between Parsons Tunnel and Teignmouth pending the completion of Phase 5.

Answer

Answered by Simon Lightwood, 17 Jul 2025

We are continuing to fund drainage and ground investigations that will provide Network Rail with detailed data on the stability of the cliffs above that section of route and will inform their consideration of a proposal for a long-term solution in due cou...