Asked by Martin Wrigley

To ask the Secretary of State for Science, Innovation and Technology, if she will make an assessment of the potential impact of the delay to the gigabit broadband target to 2032 in Newton Abbot constituency.

Answer

Answered by Chris Bryant, 3 Jul 2025

Openreach is delivering a Project Gigabit contract in the Newton Abbot constituency, that is expected to run until 2030. The first connections are expected to be made early next year.