Written questions

High Rise Flats: Insulation

Lords · Question HL6165 · Tabled 25 Mar 2025 · Ministry of Housing, Communities and Local Government · Official record

Answered 8 Apr 2025

Question

Asked by Lord Wigley

To ask His Majesty's Government by what date they expect the work to remove dangerous cladding from high rise residential buildings in England to have been completed.

Answer

Answered by Baroness Taylor of Stevenage, 8 Apr 2025

No leaseholder in a high-rise residential building should wait a day longer for remediation than necessary. The Remediation Acceleration Plan published last December states that by the end of 2029 all high rise buildings (18 metres and over) with unsafe c...