M25: Repairs and Maintenance
Commons · Question 37087 · Tabled 10 Mar 2025 · Department for Transport · Official record
Answered 14 Mar 2025
Question
Asked by Zöe Franklin
To ask the Secretary of State for Transport, for what reason hon. Members representing local constituencies were recently informed of delays to the completion of M25 junction 10 works; and what the cost to the public purse is of those delays.
Answer
Answered by Lilian Greenwood, 14 Mar 2025
The project has been delayed due to a number of factors. Severe weather, with unexpected heavy rainfall since October 2023 caused poor ground conditions. This postponed planned winter work and required a redesign of embankments and drainage. Additionally,...