Commons · Question 37087 · Tabled 10 Mar 2025 · Department for Transport · Official record

Answered 14 Mar 2025

Question

Asked by Zöe Franklin

To ask the Secretary of State for Transport, for what reason hon. Members representing local constituencies were recently informed of delays to the completion of M25 junction 10 works; and what the cost to the public purse is of those delays.

Answer

Answered by Lilian Greenwood, 14 Mar 2025

The project has been delayed due to a number of factors. Severe weather, with unexpected heavy rainfall since October 2023 caused poor ground conditions. This postponed planned winter work and required a redesign of embankments and drainage. Additionally,...