Written questions

Sewage: Peterborough

Commons · Question 28024 · Tabled 3 Feb 2025 · Department for Environment, Food and Rural Affairs · Official record

Answered 11 Feb 2025

Question

Asked by Steve Barclay

To ask the Secretary of State for Environment, Food and Rural Affairs, when the operator of the Peterborough Stanground Thistle Drive Pumping Station fitted an early duration monitor on the combined sewage overflow.

Answer

Answered by Emma Hardy, 11 Feb 2025

Peterborough Stanground Thistle Drive Pumping Station has an EDM (Event Duration Monitor) on site as this is now a legal requirement for sites that discharge storm sewage. Further information on EDM data across the UK can be found at Storm Overflow Spill ...