National Holocaust Memorial Centre and Learning Service
Lords · Question HL4243 · Tabled 21 Jan 2025 · Ministry of Housing, Communities and Local Government · Official record
Answered 13 Feb 2025
Question
Asked by Baroness Deech
To ask His Majesty's Government, further to the remarks by the Parliamentary Under-Secretary of State for Levelling Up, Housing and Communities on 22 May 2024 (HC Deb cols 975-6) that £18 million had already been spent on the planned UK Holocaust Memorial
Answer
Answered by Lord Khan of Burnley, 13 Feb 2025
From 1 April 2023 to 22 January 2025 £2.71 million has been spent on project costs, including work on the Holocaust Memorial Bill, preparations for redetermination of the planning application and preparation for the commencement of construction. £1.66 mil...