Torpedoes: Procurement
Commons · Question 25177 · Tabled 21 Jan 2025 · Ministry of Defence · Official record
Answered 24 Jan 2025
Question
Asked by Gregory Campbell
To ask the Secretary of State for Defence, pursuant to the Answer of 19 December 2024 to Question 20149 on Torpedoes: Procurement, how much of the cost is the through life management of the programme.
Answer
Answered by Maria Eagle, 24 Jan 2025
The total funds allocated for the Spearfish torpedo programme are approximately £1154 million which includes the approximate cost of £626 million for the through life management of the programme.