Written questions

National Holocaust Memorial Centre and Learning Service

Lords · Question HL4207 · Tabled 20 Jan 2025 · Ministry of Housing, Communities and Local Government · Official record

Answered 13 Feb 2025

Question

Asked by Baroness Deech

To ask His Majesty's Government, further to the Written Answer by Lord Khan of Burnley on 20 January (HL3595), whether there has been any further expenditure on the planned UK Holocaust Memorial and Learning Centre since the £138.8m estimate of March 2023

Answer

Answered by Lord Khan of Burnley, 13 Feb 2025

From 1 April 2023 to 22 January 2025 £2.71 million has been spent on project costs, including work on the Holocaust Memorial Bill, preparations for redetermination of the planning application and preparation for the commencement of construction. £1.66 mil...