Railways: Dawlish
Commons · Question 20068 · Tabled 13 Dec 2024 · Department for Transport · Official record
Answered 19 Dec 2024
Question
Asked by Martin Wrigley
To ask the Secretary of State for Transport, if she will make an estimate of the potential impact of the timing of the funding for phase five of the Dawlish Rail Resilience Programme on the cost of phase four of that programme; and whether she plans to se
Answer
Answered by Simon Lightwood, 19 Dec 2024
Decisions in relation to a phase five of the South West Rail Resilience Programme do not impact the cost of phase four, for which all physical works have now been completed. Phase five is being considered as part of the Spending Review in 2025.