Asked by Ben Spencer

To ask the Secretary of State for Transport, what discussions she has had with National Highways on when each concrete section of the M25 within the Runnymede and Weybridge constituency will be treated with next generation concrete surfacing.

Answer

Answered by Lilian Greenwood, 16 Dec 2024

The precise dates for treatment of individual sections will be determined based on regular monitoring of the condition of the carriageway. National Highways plans to give priority to treatments within the Noise Important Areas (NIA) identified by Departme...