Motorways: Leeds

Commons · Question 19013 · Tabled 10 Dec 2024 · Department for Transport · Official record

Answered 16 Dec 2024

Question

Asked by Jerome Mayhew

To ask the Secretary of State for Transport, what estimate her Department has made of the completion date of the M621 Junction 1-7 enhancements.

Answer

Answered by Lilian Greenwood, 16 Dec 2024

The schemes in question are in different stages as follows: Four schemes have been completed and are open to traffic.Scheme NameCompletion DateM621 Junction 1-7 EnhancementsCompleted September 2024A585 Windy Harbour to SkippoolCompleted March 2024A19 Down...