Written questions

Aquind: Electricity Interconnectors

Commons · Question 16873 · Tabled 28 Nov 2024 · Department for Energy Security and Net Zero · Official record

Answered 3 Dec 2024

Question

Asked by Amanda Martin

To ask the Secretary of State for Energy Security and Net Zero, when he will publish a decision on the AQUIND Interconnector project.

Answer

Answered by Michael Shanks, 3 Dec 2024

The Secretary of State continues to follow the process stated in his letter of 12 July 2024 to AQUIND Limited and the Ministry of Defence regarding considering the MOD’s representations. The 12 July 2024 letter and further updates can be found on the Plan...