Written questions

Sizewell C Power Station: Finance

Commons · Question 9522 · Tabled 16 Oct 2024 · Department for Energy Security and Net Zero · Official record

Answered 25 Oct 2024

Question

Asked by Wera Hobhouse

To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 14 October 2024 to Question 6413 on Sizewell C Power Station: Finance, for what reason disclosure of the proportions of capital allocated by Sizewell C Ltd is consid

Answer

Answered by Michael Shanks, 25 Oct 2024

Sizewell C’s spending plans are agreed by shareholders, including Government. The public disclosure of detailed spending plans whilst the project is engaged in live commercial negotiations could have a negative impact on the project’s negotiating position...