Asked by Ben Spencer

To ask the Secretary of State for Transport, what recent discussions he has had with National Highways on (a) the expected completion date for works on the Painshill junction of the M25 and A3 and (b) the steps being taken to (i) ensure the timely complet

Answer

Answered by Lilian Greenwood, 12 Sep 2024

National Highways are due to complete the main works at the Painshill roundabout and junction 10 of the M25 by Summer 2025 however, there will be other minor works including environmental enhancements that will be completed towards the end of 2025. To ens...