Asked by Baroness Deech
To ask His Majesty's Government what assessment they have made of the performance of Network Rail in replacing the Oxford railway bridge which has involved closing the main road (A420) into the city centre for the past 16 months and postponing the reopeni
Answer
Answered by Lord Hendy of Richmond Hill, 16 Sep 2024
Network Rail has not undertaken an assessment of the impacts and social costs resulting from the continuing closure of the A420 (Botley Road) to deliver the Oxford station improvements. Network Rail is working to produce a plan to complete the works and r...