Written questions

Great Western Main Line: Electrification

Commons · Question 3056 · Tabled 30 Aug 2024 · Department for Transport · Official record

Answered 9 Sep 2024

Question

Asked by Tonia Antoniazzi

To ask the Secretary of State for Transport, whether she plans to extend the Great Western Main Line upgrade to include electrification to Swansea.

Answer

Answered by Simon Lightwood, 9 Sep 2024

The decision taken in 2017 to not electrify the railway between Cardiff and Swansea was based on it not delivering significant journey time savings and this remains the case. Enhancements to the railway in Wales that deliver passenger benefits, including ...