Hydrogen: Production
Commons · Question 2806 · Tabled 30 Aug 2024 · Department for Energy Security and Net Zero · Official record
Answered 9 Sep 2024
Question
Asked by Martin Vickers
To ask the Secretary of State for Energy Security and Net Zero, if he will make an estimate of the cost to the public purse of meeting the 6GW green hydrogen production target by using local electrolysis; and if he will make an assessment of the potential
Answer
Answered by Sarah Jones, 9 Sep 2024
Government supports multiple hydrogen production pathways that meet our Low Carbon Hydrogen Standard and funding eligibility criteria. These are reviewed regularly. The Energy Act 2023 enables support for hydrogen production via Government funding or a le...